Customer: Graham Construction
Floor Type:
- Briggs Amasco: Waterproofing Company
- Bauder Hot Melt: Waterproofing System
Size: 1,100m2
Specification:
- Mechanical Preparation
- Vebro EP DPM Blended with Quartz
- Nominal 15mm Vebro Renovate Rapide
Graham Construction contacted ATS with a unique enquiry. Concrete roof decks had been poured into a steel deck with I beam supports. The weight caused deflection during setting. ATS were required to provide a degree of level correction with a system suitable for rapid external installation.
The roof was mechanically prepared and epoxy primed. Mesh was installed over the steel beams and an external grade fibre reinforced self smooth screed applied.
Within 10 -14 days the roofs were tested and passed fit for the installation of the waterproofing system by Briggs Amasco.
Download a PDF copy of this Case Study